The Town of Gravelbourg will undergo a significant infrastructure improvement project beginning with the decommissioning and dismantling of the 1928 water tower in August 2024. The project scope includes the replacement of water mains on 1st Avenue and a portion of Bettez St, as well as sewer pipe lining and repair.
Residents and visitors can expect intermittent disruption to services and road access. We encourage those affected to sign up for Citizen Alert and monitor this page for updates. Thank you for your patience and understanding as we embark on this major update to our water and sewer infrastructure that will improve and secure services for generations.
Updates
October 20, 2025: Water/Sewer Project Information Session

Thank you to everyone who joined us for the water/sewer info session. We hope you found it informative and helpful. Many thanks to Michael and Jordan of Associated Engineering for the coffee and donuts!
We will continue to use this page to update the public on the project.
For time-sensitive updates on potential traffic or service disruption, we encourage residents and business owners to sign up for Citizen Alert, our local messaging service.

October 15, 2025: As part of the Town’s preparations for the Water Main Replacement Project, early work is underway this week (October 15–21), including sewer cleaning and four spot repairs. Here's what to expect:
September 11, 2024: Crane is traveling to Gravelbourg on Friday, September 13. Bowl lifting day & tower dismantling scheduled for Saturday, September 14, and Sunday, September 15 (if required). All work on the tower is subject to weather.
August 29, 2024: Due to weather delays and equipment availability, the dismantling of the water tower has been postponed. Please continue to monitor this page for updates.
August 26, 2024: Due to forecasted winds/wind gusts in excess of 30km/hour, the dismantling of the water tower is now tentatively scheduled to begin on Friday, August 30 (weather permitting).
August 15, 2024: Project start date has been pushed to August 22; Priestly Demolition Inc. will commence with fencing, tank drainag,e and tank preparation. Tank lifting day is scheduled for August 27 (weather permitting).
Documents
The Town of Gravelbourg thanks the Governments of Canada and Saskatchewan for their contribution to this project. For more information, please consult the links below or contact the Town:
- Investing in Canada's Infrastructure Program funding announcement. Gravelbourg will receive over $2.5 million to increase the capacity of critical watermains on 1st Ave., Bettez St., Main St. and 7th Ave, and decommission the aging water tower.
- Signed ICIP Agreement (see pages 20-21 for project details)
- Water Tower Information Session Slide Deck (June 27, 2024, Public Meeting, Maillard Cultural Centre)
- 2018 Landmark Water Tower Inspection Report
- August 8, 2024 Press Release & Mailout to Residents
- Gravelbourg Water Tower Demolition Plan